P-06-1352 Approve the construction of the Third bridge over the Menai Strait
P-06-1352 Approve the construction of the Third bridge over the Menai Strait
This
petition was submitted by Emyr Owen, having collected a total of 362
signatures.
Text of Petition:
The Welsh Government's
Road Review Panel has finally concluded that the Third Menai crossing should
not be built due to concerns around Climate Change. Whilst we all understand
and appreciate the issues surrounding the Climate, this decision is a huge blow
for the residents of Anglesey and for anyone who regularly commutes across the
Menai Strait.
Additional Information:
The Third Menai Crossing
has been a project proposal for many years with hope it would finally be built
when the outcome of a consultation on the plans were published in 2018. However
in 2021, this project (like other road projects in Wales) was frozen to be
scrutinised by the Roads Review Panel.
Many arguments have been
made about resilience, most recently during the recent closure of Menai Bridge
which lasted 3 months, showing the nightmare of crossing Britannia Bridge with
the increased traffic volumes, and should it have to close for any length of
time then Menai Bridge certainly wouldn't be able to deal with the increased
traffic volumes.
The review even stated
that supporting the 3rd crossing would improve safety, resilience and active
travel yet concluded the project shouldn't go ahead, which makes the decision
even more confusing.
The construction of the
Third Menai Crossing should be approved, doing so can be a great catalyst to
Climate-friendly projects in the future.
Senedd Constituency and Region
- Wrexham
- North
Wales
- The Petitions Committee homepage
- View all open petitions
- View all petitions the committee is currently considering
- How the petitions system works
- Petition research briefs
Business type: Petition
Reason considered: Senedd Business;
Status: For consideration
First published: 17/07/2023