P-03-273 Transportation of Wind Turbines in Mid Wales

This page gives details of any meetings held which will, or did, discuss the matter, and includes links to the relevant Papers, Agendas and Minutes.

Note: Meeting Agenda can change at short notice. Particularly where future meeting dates are indicated more than a week in advance. Please check before planning to attend a Committee Meeting that the item you are interested in has not been moved.

Meeting: 16/10/2012 - Petitions Committee - Fourth Assembly (Item 3)

3 P-03-273 Transportation of Wind Turbines in Mid Wales

Supporting documents:

Minutes:

The Committee considered this petition and agreed to close the petition, given that:

 

The broader issue had been addressed by the Environment and Sustainability Committee’s Report on Energy Planning and Policy in Wales, which had been published in June 2012; and

The petitioner had not responded to a request for further comments on the issue.

 


Meeting: 17/07/2012 - Petitions Committee - Fourth Assembly (Item 3)

3 P-03-273 Transportation of Wind Turbines in Mid Wales

Supporting documents:

Minutes:

In light of the publication of the Environment and Sustainability Committee’s report of inquiry into Energy Planning and Policy in Wales, the Committee agreed to ask the petitioners whether they have any final comments to make before bringing consideration of the petition to a close in the autumn.

 


Meeting: 27/09/2011 - Petitions Committee - Fourth Assembly (Item 3)

3 P-03-273 Transportation of Wind Turbines in Mid Wales

Supporting documents:

Minutes:

The Committee considered an update to this petition.

 

Actions

 

The Committee agreed to defer consideration of the petition until the outcomes of the Environment and Sustainability’s inquiry into energy policy and planning are known.

 


Meeting: 14/07/2011 - Environment and Sustainability Committee - Fourth Assembly (Item 4)

4 Petitions: P-03-273 Transportation of wind turbines in Mid Wales & P-04-324 Say No to TAN 8 – Windfarms and High Voltage

Supporting documents:

Minutes:

4.1 The Committee considered the petitions and agreed that they should be incorporated into its inquiry into Energy.

 

4.2 The Chair would formally respond to the Chair of the Petitions Committee.


Meeting: 12/07/2011 - Petitions Committee - Fourth Assembly (Item 3)

3 P-03-273 Transportation of Wind Turbines in Mid Wales

Supporting documents:

Minutes:

The Committee considered an update to this petition.

 

Action

·         The Committee agreed to refer the petition to the Environment and Sustainability committee for further consideration

·         The Clerk to clarify whether the responsibility for the transportation aspect of windfarm developments over 50MW is retained by the UK Government

·         Dependent on the answer, the Committee agreed to write to the Department of Energy and Climate Change to seek its views on the issues raised by the petition.